Project Update
The Quad Business Towers
During the month of September, construction works at The Quad continued on schedule. Levels 11, 09, 12 and 13 in Towers Q1, Q2, Q3 and Q4 respectively have been roofed over, with vertical construction works on the overlying floors ongoing.
The installation of mechanical and electrical services is continuing at all basement levels including the tower cores. Marble works in basement levels have commenced, whilst plastering works of the tower cores at all basement levels as well as within Tower Q3 are progressing well.
The installation of the rainwater and sewer systems is continuing and the floor-to-ceiling façade is being installed in all the lower floors of the towers.
The two steel bridges linking Towers Q2 and Tower Q3 are now in place with the next two bridges linking Towers Q3 and Tower Q4 presently being manufactured.